2006 PALLADIO AWARDS
Sympathetic Addition
WINNER:
ARCHITEXAS
Now the Bells Toll
PROJECT: Tower addition to Cathedral Santuario de
Guadalupe, Dallas, TX
ARCHITECT: Architexas – Architecture, Planning and
Historic Preservation, Inc., Dallas, TX; Gary Skotnicki,
principal in charge; Richard Martratt, project
architect; Jay Firsching, David Chase, Carrie Zaboroski,
Elizabeth Cummings, Jeff Cummings, associates
GENERAL CONTRACTOR: Andres Construction Services,
Dallas, TX
STRUCTURAL ENGINEER: Jaster-Quintanilla, Dallas, TX;
Steven, H. Lucy, PE
LIGHTING DESIGN: Lindsley Architectural Lighting;
Alan Lindsley, principal
ELECTRICAL ENGINEER: OLA Consulting Engineers,
Dallas, TX
The Sacred Heart Church in Dallas, TX, now the Cathedral
Santuario de Guadalupe, was designed in the 1880s by
noted Galveston, TX, architect Nicholas J. Clayton with
tall towers on the south façade. It was completed in
1902, but the spires were not built at that time,
presumably for financial reasons. The bases were there,
but they were capped with simple wood-framed hipped
roofs.
A later, simpler design by Clayton incorporated one tall
tower and a shorter one, and a still later third design
in 1907 featured a Beaux-Arts tower with a clock. Now,
after more than 100 years, the church has finally
completed the towers, the tallest housing a 49-bell
carillon and clavier, thanks to a $4.7-million project
and the design efforts of Architexas of Dallas, TX.
“The new design is an adaptation of Clayton’s second
version,” says Jay Firsching, preservation specialist at
Architexas. “We felt like the middle design most closely
matched the style of the building as it was intended to
be constructed,” he explains. “These are also the more
detailed and developed of Clayton’s drawings, so they
were interpreted and adapted in designing the new
towers.
”This project presented a number of design and engineering
challenges. First, the towers had to be compatible with
and enhance the original historic building. Secondly,
the taller of the two had to support the new quite-heavy
carillon requested by the diocese. The new spire adds
135 ft. to the original base to reach a height of 219
ft. from the ground floor (224 ft. from grade) and
supports the 49-bell carillon system weighing 49,000
lbs. and a clavier (keyboard) to play the bells.
Manufactured in the Nether-lands, this particular
carillon includes 45 static bells, the largest weighing
2,200 lbs., and four swinging bells, the largest
weighing 9,400 lbs. It was quite a challenge to hoist
these bells into place, with the largest and highest
bells located 146 ft. above street level.
“We had to interpret the original 1/8-in. scale drawings
based on the existing detailing of the cathedral,” says
Gary Skotnicki, Architexas’ principal in charge, and the
person charged with adapting the historic design. “The
original structure is load-bearing solid masonry with
interior timber framing. We had to determine the best
way to detail and construct the new tower addition to
fit within Clayton’s intentions while meeting today’s
building codes.
”To accommodate the massive weight of the bells as well as
the new 224-ft. west tower itself without adding stress
to the original 106-year old building, Architexas and
the engineers determined that the structure would have
to be supported from the ground up. “The base of the
tower is about 20-ft. square, with 28-in.-thick
load-bearing masonry walls on a corbelled masonry
foundation extending 4 ft. below grade,” Skotnicki
explains. “The design team decided that the new tower
extension should stand independently from the existing
masonry base, but appear to be part of the existing
structure, as if the building had been originally
completed all the way up to the spire and cross.
”These goals were accomplished by excavating a 35-ft.
square around and inside the existing structure to the
bottom of the footings. Four piers, each 18 in. in
diameter, were then drilled to a depth of 56 ft.,
protruding 8 ft. into the underlying limestone
substrata. Two 24x54-ft. slots were cut through the
corbelled footings and each face of the tower base.
Reinforcing steel cages made up of #11 rebar were placed
around and through the existing masonry footings. Seven
thousand pounds of concrete were then poured,
integrating the old and new foundations. The resulting
pad contains 90,000 lbs. of steel and was designed to
carry four 14-in. square columns to support the new
tower extension above.
Once the foundation was in place, the steel inner frame was
inserted into the tower, which had been gutted. The roof
was removed and prefabricated steel structural sections
were hoisted, one at a time, over the top of the
existing masonry walls and lowered carefully down into
the tower. There was only ½-in. clearance from the
existing walls. The fourth of these sections brought the
structural frame above the existing masonry and the
fifth section formed the 36-ft.-tall bell chamber. The
final prefabricated steel section was erected and welded
on the plaza and hoisted as one assembly to form the
dormer level. The last piece was the aluminum-framed,
copper-roofed steeple. It was constructed offsite by
Campbellsville Industries of Campbellsville, KY, shipped
to the site and lifted into place.
“Most of this work was done at night because we weren’t
allowed to close any of the major streets during the
day,” says Richard Martratt, project architect,
Architexas, “and we had to use large cranes to lift the
sections into place. After each section was lifted into
place in the tower, we would work on it for a few weeks.
It took quite a while to weld those sections in place
and to get ready for the next ones. Plus you had the
interior elements – several bell levels and various
support brackets and also the stair itself – that had to
be welded in place.
”Hoisting the bells into place was another challenge. The
contractor, Andres Construction Services, Dallas, TX,
used a combination of systems. A hydraulic platform
scaffold system capable of supporting 16,000 lbs. with a
climbing speed of 100 ft. every 50 min. did part of the
heavy lifting. The platform scaffold was also equipped
with a material hoist with a lifting capacity of 2,500
lbs. and a travel distance of 80 ft. A cantilevered
trolley beam and pneumatic trolley hoist with a lifting
capacity of 10,000 lbs. was installed above the upper
bell chamber. These systems were used together to
carefully lift the bells into place in the two bell
chambers.
“Hoisting the bells was difficult because we had to snake
them through the steel structure,” says Martratt.
“Lifting a nine-ton bell and snaking it through the
structure is quite a feat. We built some lifts on the
outside of the tower that were used to transport them to
a certain height, then we used a system of levers and
pulleys to get the bells into exact position.” This work
could be done during the day because it didn’t require
cranes and the streets didn’t have to be closed. Those
same platforms were used when cladding the building and
doing other exterior construction.
At one point, Martratt points out, the vibration of the
bells was a big issue. “When we got the bells installed
and began to ring them for the first time, the whole
frame began to sway,” he says. “We were getting about
¾-in. vibration. We got the engineers involved again to
take another look at it. We figured out that the
frequency of the vibration was the same as the steel
frame, so it excited the steel frame, causing it to move
when the bells rang.” The problem solved itself when the
building was loaded with masonry. The primary materials
used to clad the new section of the spire were red
hard-fired brick, cast stone and copper. These were
selected to blend with the historic structure, according
to Skotnicki, “to fit seamlessly into the historic
building. It was a bit of a challenge to match the
original brick, but we came close.
”The shorter tower was a simpler project. It also had a
hipped roof, which was removed and replaced with a
copper-roofed steeple from Campbellsville Industries.
This added almost 41 ft. to the tower, bringing the
height to 102 ft. “We did some exterior repair work, but
we didn’t have to do the foundation work because the
tower was not increased in size,” Firsching notes.
Construction started in June of 2005 and was completed in
November of 2005 without disrupting the normal services
and operations of the cathedral. The new spire more than
doubles the height of the building and it finally
fulfills the goals of the original design of the
cathedral. In addition, it allowed the church to add the
massive carillon, fulfilling the diocese’s goal of
bringing a level of prominence to the cathedral.
Skotnicki points out that this is the largest carillon
(by one bell) in Dallas and the second largest in Texas,
second only to the one at the University of Texas in
Austin.
The Cathedral Guadalupe serves one of the largest cathedral
congregations in the United States, with an average
Sunday mass of almost 10,000 parishioners. The new
towers are just one phase of a comprehensive set of
improvements being undertaken for the cathedral and its
surrounding buildings and plazas. “We began working with
the diocese in 1995,” says Skotnicki, “when Architexas
completed a master plan prioritizing the work into
manageable phases that minimize the impact of
construction on daily services.
”Previous work included the integration of new mechanical
systems into the building, redesign of the altar and
exterior restoration of the building’s two primary entry
bays. Future phases will focus on the plazas,
restoration of the sanctuary, and completion of the
exterior restoration.
“This is the most dramatic of the work so far,” Skotnicki
says. “Nicholas J. Clayton would have been very happy
with the new addition. His grandson and great grandson
participated in the groundbreaking and the dedication.
Everyone is happy with it.” – Martha McDonald